Wednesday, April 24, 2013
(old)Days of Re"SEARCH"
In
Post- independent India Development has become a catchword to gain public
support for resource redistribution. Under the leadership of influential
national leaders like first Indian Prime Minister Jawharlal Nehru, state
initiated resource extraction and developmental activities like steel plants
construction, mineral extraction, dams’ construction. As the Indian citizens
had immense belief in the new Indian leadership and democracy, the process of
resource redistribution through land acquisition and displacement of people
from their resources were easier. The national leadership also firmly believed
in the existing theories of economic development and social development through
industrialization[1].
Economic planning and nationalization of resources were part of the dream to
become a developed country following the paths of then well-developed socialist
countries. The theoretical understanding of the process of economic development
was actually evolving during that time period. As Indian planners tried to make
Indian economy self sufficient as well as planned one, they did not change some
of the fundamental colonial powers that the state was privileged with.
Legislations that established state control over the natural resources and
formalization of the eminent domain kind
of principles were accepted as part of the development strategy. Colonial state
government has institutionalized the forceful acquisition of land on the basis
of the Land Acquisition Act 1894 and the government in post-independent India
also continued to invoke these kinds of colonial legislations. Hence the
emerged democratic structure resulted in a State-centered property right regime
in case of common resources. Forest resources, minerals, rivers and all such
natural resources also came under the state ownership. This facilitated the resource redistribution
under the industrialization-led development process which basically aimed at
the large scale resource extraction to make efficient usage of natural
resources. This reinstated the state power over community resources and the
traditional forest dwellers like tribal population started loosing their rights
over such resources. Before colonial legislation of reserving the forests under
state ownership, tribal people used to co-exist with forest and its ecosystems.
They preserved those as their community resources as they had informal and
traditional community rights over their local resources. In some of the primitive
tribal areas, still they do not have the individual property rights. Moreover
the ownership over resources, tribals protect their resources due to their
unique value frameworks in which they assign metaphysical significance for the
natural resources. Indigenous communities used to worship nature and they
consider their resources as divine. As
the property rights removed from the traditional forest dwellers, their
resource ownership and livelihood options started getting challenged. Forest
departments were given the authority to safeguard the forest resources. Their
initial efforts were to remove the inhabitants and adivasis (indigenous people)
from their resources and land, despite the fact that tribal people’s
co-existence with forest for decades substantiates the sustainable community
management of resources. Land acquisitions took place in the forest lands for
the massive power generation through hydro-electrical projects, dams
construction, minerals extraction and steel and iron manufacturing etc forced
the traditional forest dwellers to move out of their resources. As the tribals
were no more the legal owners of the land (where they were living for
generations) their displacements from those resource-rich lands were easy.
Till
liberalization of the economy, most of the development projects took place
under the authority of public sector undertakings. After economic reforms in
1991 most of these projects got established under private companies and state's
role changed to that of facilitator of such industrial projects. Hence the
nature of resource extraction and the distribution of its benefits changed.
Market got an important role in materializing industrial expansion using the
unemployed resources including minerals. Regulations and controls over the
resource extraction got liberalized. Investor friendly policies and investment
facilitation became the primary interest of the governments. Ultimately, on the
one hand people who got affected from such projects got worse off and on the
other hand the ‘market preserving federalism’ as the outcome of liberalized
open national economy resulted in the fierce competition among states to
attract new investors. These aggravated the conflict between state governments
and communities who depend on their local resources for livelihood.
The institutions generated by colonial
rulers were not intended to protect the resources but meant to facilitate their
industrial resource extraction. A comparative assessment of community ownership
regime before the natural resources got nationalized and state-ownership regime
substantiate the fact that state defined property rights didn’t help to
preserve the forest resources as expected. Based on the policies initiated
during colonial time period, forest department constituted for the protection
of state's property right over natural resource in the post-independent era. Failure
of state in protecting forest resources from encroachers, timber merchants and
pouchers, as well as the injustice done towards the tribal and non-tribal
forest dwelling classes along with the change in theoretical understandings
about property right and open access problem of community resources reflected
in the new policies like FRA 2006. This theoretical as well as policy level realization
about the significance of forest dwellers in protecting the resources and their
interdependence with their surroundings led to the Forest Rights Act 2006. The biggest FDI proposal India has ever got
was the POSCO FDI proposal signed in 2005. As FRA came into existence by 2006,
POSCO land acquisition that included forest land was expected to fulfill the
FRA criterion. As the policy initiative was to ensure that the rights of forest
dwelling class of people is not getting violated and that their rights over
resources are respected in case of resource redistribution for any
developmental activity. Even then in case of forest clearance for the project,
a clear cut institutional failure happened in POSCO case and the role assigned
to local people got discarded in the whole process. Theory and policy making
are complementary to each other, but while implementing the policies
institutional barriers and functional problems cause a wide realization gap.
This realization gap cause further deviations in the integration of research
and policy making. This empirical analysis will help to assess the gap that
exists between policies and practice in development; and to understand what
prevents the research understandings from materializing and benefiting the
process of development.
Theoretical understanding leading
to policy measures
Environmental
sustainability and the externalities of industrialization got the attention of
policy makers and the result was the establishment of a nodal agency of the central
government of India which is primarily intended for the conservation of the
country's natural resources and for the prevention and abatement of pollution.
This is the Ministry of Environment and Forests (MoEF). MoEF established
initially as National Council for Environment Policy and Planning within the
Department of Science and Technology, following the 1972 United Nations Conference
on the Human Environment in Stockholm. Later on MoEF has been given a prominent
role in the national policy making and currently environmental clearances are
crucial for any industry to be established. Importance given to sustainability
and environmental protection in policy making is the direct result of new
findings in development theory that expanded the meaning of development to a
broader sense of sustainable development that enhances people to expand their
opportunities. Few of the policy developments are explained here.
1. Forest Rights Act 2006 (FRA)
FRA
enacted “to recognize and vest the forest rights and occupation in forest land
in forest dwelling scheduled Tribes and other forest dwellers who have been
residing in such forests for generations but whose rights could not be
recorded, and also forest rights on ancestral lands and their habitat were not
adequately recognized in the consolidation of state forests during the colonial
period as well as in independent India resulting in historical injustice to the
forest dwelling scheduled tribes and other traditional forest dwellers[2]
who are integral to the very survival and sustainability of the forest system.”
FRA ensures the rights of forest dwellers as individuals who use the resources
as well as the communities that co exist with the given environment. FRA
recognizes village level local governance bodies (Gram Sabhas[3])
as the guardians of their ecosystems. It laid down clear procedures to verify
these claims and acknowledges community's right to take free, informed decision
about giving consent to govern the ecosystems. If the forest land needs to be
diverted for some industrial or other development purpose then the permission
or agreement of these forest dwellers is essential according to the FRA. Hence
their rights over their ancestral land for which they may or may not have records
of legal ownership are recognized as their own land and land acquisition can
happen only with the consent of the forest dwellers and further, all such
acquisitions must be adequately compensated for.
2.
Environmental Clearance
MoEF
gives two clearances for developmental initiatives – one for using forests under the Forest
Conservation Act 1980 and another under Environment Protection Act – called the
Environmental clearance. Forest Conservation Act 1980 restrains the use of
forest lands for non forest purposes. Forest clearance from central government
is needed for any project to start in forest land according to this. According
to the Ministry of Environment & Forests (MoEF) “The basic objective of the
Act is, to regulate the indiscriminate diversion of forest lands for
non-forestry uses and to maintain a logical balance between the developmental
needs of the country and the conservation of natural heritage.” State
government has to get approval from central government to use reserved forest
land for any non forest purpose and state government cannot lease forest land
to any private parties that are not controlled or managed by government. The
Environment (Protection) Act (EPA) was enacted in 1986 with the objective of
providing protection and improvement of the environment. EPA empowers the
government to make rules to regulate environmental pollution, by stipulating
the ambience standards setting maximum limits on the discharges of pollutants
into of the environment - air, water, and soil. After FRA came into existence
the ministry in 2009, made its clearance process comply with the Forest Rights
Act (FRA) and demanded approval from village councils before permitting mining
in the forest area.
3. Environment impact assessment
The
term Environment Impact Assessment (EIA) refers to the anticipation of various
impacts a project will have on the environment and the local community. It is a
decision making tool, which guides decision makers in taking appropriate
decisions prior to sanctioning clearance. The
EIA
Notification falls within the umbrella act – The Environment Protection Act,
1986. Environmental impact assessment ensures public participation in
the decision process. Public consultation in the regulatory process is
expected to help the decentralization of power also. Public hearing is an
opportunity for the local people to express their concerns regarding the impacts of the proposed project,
which also make the development process more democratic at the ground level.
EIA is a pre-requisite for obtaining environmental clearance.
4.
Rehabilitation
People's
opposition to mega projects that displace them and negatively affect their
livelihoods and living standards intensified following the lack of
identification of people's right in decision making. Communities that tried to
oppose such projects were blamed for acting against national interest and their
grievances were not taken into account properly. People who got affected by
land acquisition and other negative externalities of proposed projects failed
to get any identification from state authorities. These conflicts got
intensified during the nineties after liberalization. As land acquisition
became a grave issue in the process of development, rehabilitation and resettlement
policies enacted. National Rehabilitation and Resettlement Policy, 2007 aimed
at ensuring rehabilitation and resettlement of persons affected by the
acquisition of land towards projects described as serving a public purpose or
involuntary displacement caused due to any other reason. But Rehabilitation
policy 2007 failed to ensure a proper rehabilitation scheme in the system and
the grievances of the project affected people has not got addressed properly.
As people had serious issues with the existing model of resource redistribution
and land acquisition, most of the projects proposed even after the
implementation of NRRP 2007 faced public protest. Especially in mining and
mining related projects, the dissidence from the part of indigenous people
mostly tribal people in the forest areas was very evidential. As the central government realized the importance
of local people's support for any the successful working of any development
project, attempts for a new rehabilitation policy started from the government's
side. Draft of National Land Acquisition and Rehabilitation & Resettlement
Bill, 2011 is an attempt to balance the need to facilitate land acquisition for
various public purposes including infrastructure development, industrialization
and urbanization, and to address the concerns of farmers and those whose
livelihoods are dependent on the land being acquired. This draft Bill is proposed
with primacy over other specialized legislations like laws for highways, SEZ's,
railways etc. This law prohibits private companies from purchase of
multi-cropped irrigated land for public purposes. Social Impact Assessment
(SIA) is made mandatory as per the draft bill, which ensures that the Gram
Sabha is consulted and the SIA is made available for the public scrutiny. This
new Bill is meant to ensure “a humane, participatory, informed, consultative
and transparent process”; and guarantees that the cumulative outcome of
compulsory acquisition should be that affected persons become partners in
development.
POSCO
Project: The biggest FDI and the strongest protest
POSCO
signed the memorandum of understanding (MoU) with Orissa state government in
June 2005, to set up a 12 million tons per annum (MTPA) green field steel plant
near Paradip, Jagatsinghpur District, Orissa, with an estimated investment of
$12 billion USD (Rs.52,000 crores) which is the largest ever Foreign Direct
Investment (FDI) initiative since Indian economy liberalized in 1991. This
proposed steel plant needs to acquire land from eight villages in three gram
Panchayats, namely Dhinkia, Nuagaon and Gadakujang in Jagatatsinghpur district
of Orissa. The plant would require a total of 1620.496 hectares of land of
which 1253.225 hectares is forest land. Official statistics show that only 438
acres of the 4,000 acres required for the POSCO site are private land, the rest
being government land, recorded as ‘under forest’ but most of this land is under
betel, cashew and other cultivation for years and the local people have a right
in this land as per the Forest rights Act. Local inhabitants whose land was
earmarked for the project and whose livelihood was going to be adversely
affected due to the displacement started their protests from the time when the
MoU signed. Various groups like POSCO Pratirodh Sangram Samiti (PPSS) started
forming from August 2005 onwards and they use different strategies of protest
against the project including the blockage of the entry of any government or
POSCO official into three (Dhinkia, Gada Kujanga and Nuagaon) of the nine
villages earmarked for the POSCO project.
Opposition
to the POSCO project has been continuing for the last 7 years. People and
groups that oppose the project raise various issues regarding the POSCO project
including the “subversion of state’s authority and sovereignty for POSCO’s
benefits”(MZPSG's report (2010) http://miningzone.org), impoverishment and loss
of livelihood threat of the villages that face displacement for the project and
other socio-economic issues. The current local economy is a well-flourished
agrarian one, which provides good living standards for the residents; they
prefer it over the new one promised by POSCO. Justice of trading off the rights
of some people for the so called “national interest” which is a claim that is
not substantiated or clearly defined yet is continuously questioned by local
people. They demand the state government to enter into discussions with them
about the project implementation and land acquisition for the project. State
authorities failed to respond to their demands and state and central government
still try to initiate the project there against the wish of the local people.
As POSCO investment is considered by the authorities as a green signal for the
“economic development” of the state and also country, the local people who face
the threat of displacement consider it as a devastating change that will cause
destitution for them. This conflict of interests of government and local people
prevented the initiation of the project even after seven years. In between, the
project has got all the approvals from authorities like that of Forest
clearance, Environmental clearance and sanction to start with land acquisition.
But it is already exposed that most of these clearances POSCO has got without
fulfilling the essential criteria and state government functioned in a
completely biased way to retain the investment.
Development:
how it differ for government and local people
As
per the MoU between government of Odisha and POSCO, the benefits offered
includes road and rail that link the steel plant with the port, township made
for the employees of POSCO, power plant made for meeting the needs of POSCO
steel plant and the full project (including iron ore mining, steel plant
including captive port) which is claimed to create an additional employment of
50,000 person years annually for the next 30 years and Rs.20 billion of
additional output for Odisha. Interestingly, in the NCAER cost-benefit report[4]
they describe the employment and output multiplier of iron-ore rather than that
of steel that will be produced in the plant. As a result, separate measures for
the steel plant are not available. Hence the steel plant that is proposed to
begin in Jagatsighpur is expected to contribute its share in output multiplier
of 2.36 and employment multiplier of 0.69. This means that 0.69 man-year of
employment will be created for every Rs.1 lakh output of crude steel. Hence, as
per the NCAER report the iron ore project would contribute 1.3 per cent to
Odisha’s State Gross Domestic Product (or SGDP) by 2016-17.
Most
importantly, these figures do not talk about what the 52000 crore steel plant
project itself can bring into the economy, but includes the iron ore mining
that will constitute 600 million tonnes of iron ore of an average Fe content of
62%, to meet the requirements of the proposed Steel Project of 12 million
tonnes per annum. Hence these numbers can't be inclusive of all the costs that
the society has to bear and environmental degradation that'll happen due to the
steel plant. From the point of view of the potentially displaced and project
affected people, who will directly lose their land and livelihoods for the
steel plant the benefits that are offered according to the MoU are “(viii) for
rehabilitation of displaced families, Rehabilitation and Resettlement Package
would be implemented as per prevailing guidelines and practices”. Even after
the protest and opposition from the people regarding the land acquisition and
displacement, government didn't implement the rehabilitation and resettlement
guidelines that exist in the state and central level. Later, the rehabilitation
package that was announced by POSCO following the first meeting of
Rehabilitation and Periphery Development Advisory Committee (RPDAC) which was
held five years after the signing of the MoU offered compensation package of Rs
17 lakh per acre for private land, Rs 11,500 per decimal of betel vine and Rs 2
lakh per prawn farm to be acquired for the plant. According to this package
“Altogether 718 families which included 466 original families and 252 extended
families, would be affected in the project. While each
original
family will get a 443 sq feet house on 10 decimal land in the rehabilitation
colony, the extended families will get 10 decimal land and Rs 1.66 lakh towards
compensation. This apart, a member of each nucleus family will get a job”[5].
This package got rejected by the local farmers and other villagers. These
farmers and others who are dependent on the betel vine economy can earn more
income by continuing their current livelihoods[6].
As per the MZPSG's (Mining Zone People’s Solidarity Group) report[7],
“the average net income yield per decimal of betel vine ranged between
Rs.37,000/ decimal (at Rs.0.57/leaf) and Rs.40,000 (at Rs.0.60/leaf). The
minimum recorded per decimal yield was Rs.32,000, and the maximum per decimal
yield recorded was Rs. 50,000 ”(MZPSG Report; Iron and Steel: The POSCO-India
story, 2010, pp. 35). Hence the compensation that is offered for their betel
vine yards that can earn them annual incomes of around Rs 40000 seems
negligible for the local people. And the report of the Committee Constituted to
investigate into the proposal submitted by POSCO India Pvt. Limited for
establishment of an Integrated Steel Plant and Captive Port in Jagatsinghpur
District, Orissa steel plant will displace and reallocate these farmers to
utter destitution without any such livelihood option. Betel vine yards can
accommodate people of varying age groups into employment due to the nature of
work that its cultivation offers. Landless workers also prefer betel vine
economy over the industrial one offered by POSCO. MZPSG's report concludes that
“paan kheti employment was preferable to industrial employment, since they were
able to find work regularly and at wage rates far higher than the Orissa
minimum wage” (MZPSG report, 2010, pp.35). The fallacy of employment generation
by POSCO project is questioned in the MZPSG's report. The employment multiplier
for iron ore mining and steel production as well as the employment generation
proposed in the NCAER report is questionable because the projected calculations
in the report are on the basis of a strong and false assumption that the
sectoral linkages would remain unchanged for the duration of the project –
which is around 30 years. Moreover, the potential employment is predicted based
on unrealistic assumptions about technology and prices. While in reality,
technological changes in the mining and related sectors have been labor
displacing and this is not taken into account. Further, the arbitrary
assumption of constancy of price of steel makes the employment predictions less
reliable. The potential employment opportunities generated through backward linkages
by POSCO are also low since the NCAER report notes that “POSCO‐India assumes that
imported procurement is 65 per cent of total input materials" and hence
only the remaining 35% of its inputs will be sourced from India[8].
Moreover, baseline figures of current livelihoods in the three Gram Panchayats
are not taken into account in the current analysis. Hence, as the MZPSG's
report suggests, the benefits that can be brought to the national and state
economy need to be reviewed after considering all these flaws with the current
cost-benefit analysis done. Both NCAER and MZPSG's reports deal with the whole
project including the steel plant, captive port and the mining. As this
dissertation mainly takes into account the steel plant project that is proposed
in Jagatsighpur, further analysis will be limited to this dimension of the
problem, although the broad background of whole project will be taken into
account. On the basis of the limitations of the reports pointed above, the
claims of massive employment generation and growth prospects that will be
generated from POSCO project are often exaggerated or unfound.
In
what follows, the impact on the local economy and people is deliberated
further. As it is already mentioned, local farmers and daily workers can't get
improved average incomes due to the project. The compensation offered to the
betel vine farmers is much lesser compared to their life time earnings from the
current agrarian economy. In the existing local economy the landless daily wage
laborers get work regularly at a wage rate far higher than the stipulated
minimum wage in Odisha45. If the affected sections from these categories of
employment were to accept employment in POSCO steel plant as an alternative,
then they would become contract workers, which are characterized by no job
security, low wages, gender inequities in pay, and sexual harassment46. Existing
local economy ensure steady agrarian employment due to the nature of betel vine
cultivation, which is far more protective in social terms also compared to the
informal work in the industrial sector. There is a likelihood of the local
workers being replaced by other migrant workers and there is no protection
against such a substitution. In mining sector, level of mechanization is highly
increasing and such technological changes could also displace workers and there
is no protection against such displacement. Moreover, in addition to the point
already made that the incomes of the people are likely to suffer a decline;
past experiences suggests a possibility of an increase in the average household
expenditures following the implementation of the project. This is due to the
intricate links between the social, economic and ecological aspects of life
amongst these communities. Firstly, the affected people can no more have access
to farming and other community commons they used to have access to prior to the
project, they may have to depend on the markets to meet these demands. This
will imply additional expenditures on their daily consumption of various goods
like water, firewood, vegetables etc. Secondly, the project is likely to cause
a collapse of current agrarian economy which would definitely let them earn a
higher income under relatively healthy working conditions compared to smelting
and other steel processing activities in a steel plant which will involve
greater occupational risks without any occupational risk compensations.
Further, other comforts of life that are anticipated as a consequence to modern
development like electricity, telephone connectivity, modern health care,
education systems etc., are not assured by the company or the government to the
affected people. Rail- road connectivity offered and power generation ensured
in the project is only for the benefit of steel plant and these benefits do not
accrue to the local people. This ‘investment led development’ does not ensure
any improvement of well-being for the local people. This causes strong
opposition from potentially project affected communities.
Rehabilitation
is not accepted as an agreeable alternative for the current local economy and
the evidence prove that POSCO project does not work as a “development project”
for the potentially affected people. Considering this fact, any policy measure
to improve the rehabilitation and resettlement can't work here. A very
important observation needs to be done here is that, even the existing
rehabilitation policy does not allow displacement of people without their
permission and agreement. But this policy norm gets violated easily. The main
reason for such an inherent contradiction in policy and practice is the
structural flexibility in governance system to overcome protective policies
with more authoritative growth intended policies. This becomes easier in the
current situation where dominant regime of market led growth is generally
accepted as a national policy. The social reaction and defects with the current
model of development get noticed by the activists and academicians, and the efforts
to include those social externalities into account are already taking place.
Policy implications of such efforts also come out as in the case of FRA 2006.
But the realization gap that distances such policies and research from practice
and more importantly from the real outcomes needs to be analyzed. Otherwise all
the research that take place in development theory will go in vain. The gap
between realization and policy making cause further defects in the theoretical
understanding of the developmental problems, if the realization gap is not
identified fully.
Realization
Gap
In
POSCO case, property rights are clearly defined. Non-forest private land
demarcated for land acquisition clearly belongs to private owners. Forest land
comes under the theoretical introspection of definition of property rights.
Before 2006 FRA enactment, forestland defined as under state ownership. Environmental
Impact Assessment is a legislation meant for the protection of environment and
local communities that get affected by a project. Before a project obtains
statutory environmental clearance from the Ministry of Environment and Forest
(MoEF), it has to produce an EIA. EIA notification requires a public hearing to
be done “in a systematic, time bound and transparent manner ensuring widest
public participation at the project site(s) or in its close proximity". To
conduct this mandatory public hearing, a notification has to be given in all
the major local and national daily news-papers one month before the public
hearing. The EIA reports must be provided to the concerned Panchayats. A Gram
Sabha must be organized where the EIA report has to be discussed and based on
the majority opinion, a decision has to be arrived at about the project in
question. The Public hearing is meant to listen to the views of the community.
It’s a forum where the local people could air their doubts, grievances and problems
pertaining to the project. It is also a platform where opposing interest groups
can freely express their views. Public hearing is the one and only
participatory forum people have, to express their views on the development
project in case of non-forest land. State pollution control board is the
institution that needs to conduct the public hearing for the environmental
clearance. In most of the cases public hearings are conducted in a haphazard
manner and are thus reduced to a mere formality[9].
In
POSCO EIA on 15 April 2007, a joint public hearing as per the Environment
Impact Assessment (EIA) Notification 2006[10]
was conducted for the captive port and first phase of the steel plant. Public
hearing conducted by the OSPCB (Orissa state pollution Control Board) at
Kujanga which is 15 Km away from the project affected area. Not at project site
and not even at a “close proximity”. This clearly is a serious violation of the
objective of the public hearing that seeks to ensure widest public
participation. Public hearings are subject to complete deviation from the
spirit with which it is prescribed in the EIA notification. In various cases,
people's dissent and resistance ends up in turmoil and law and order problems
which then get reduced to conflicts between the state police and the
protesters. Authorities have often taken
an investor friendly position rather than genuinely respecting the democratic
deliberative mechanisms and people's verdict[11].
Local people can't be taken as a homogeneous group of protesters, some of them
are ready to accept the compensation and support the development projects in
the expectations of employment or good compensation and rehabilitation being
offered than their prevailing living condition. Public hearing, if conducted in
a free democratic environment can take into account all the concerns and
demands of the people. EIA report for the captive port (at Jatadharmohan Creek,
Paradeep in Orissa for supporting the 12 million tons per annum (MTPA) POSCO
steel plant) prepared by National Institute of Oceanography (NIO) has been
technically evaluated by Center for Science and Environment ( CSE). This port
is meant to support the import of coal and iron ore and to export the finished
steel products. Technical evaluation of the Marine Environmental Impact
Assessment (MEIA) done by CSE points out many defects. First of all it is
pointed out that the EIA for POSCO has been done without conducting any field
study. This reveals the lack of credibility of the EIA report. The report does
not deal with the impact of the project on Jatadhari River and its drainage
pattern. Biodiversity of the area is not considered seriously which is obvious from the fact that Olive Ridley
Turtle, enlisted as endangered species in IUCN red data book is found in the
areas proximate to the Gahirmatha Sanctuary which is located near the port and
at the mouth of Devi River the olive turtles come for nesting. Measures ought
to be taken to ensure that the raw materials such as iron ore, coal and steel
products that will be transported and stored in the port do not give rise to
fugitive dust causing air pollution. This aspect is also not mentioned in the
official EIA report. Impact on livelihoods of people who depend on betel
vineyard and cashew plantation as well as the fishing community is not
discussed in the report. POSCO got the EIA done by National Institute of
Oceanography and the EIA report which consists of such serious omissions, was
the basis on which MoEF has given environmental clearance for the project.
POSCO sought to get separate environmental clearances for steel plant and port.
This will not give the details of cumulative environmental impact of these
projects. POSCO prepared the EIA and applied for environmental clearance for 4
MTPY capacity steel plant only, while the land is demanded for 12 MTPY steel
plant[12].
Total scale of project is almost equal to combined production capacity of 6
steel plants of India (Bhilai, Bokaro, Durgapur, Rourkela, Burnpur and Salem
put together); even then POSCO got environmental clearance without doing a
comprehensive environment impact analysis (EIA). They submitted a rapid EIA
that also based on data on monsoon period for the port while data collection on
monsoon period is prohibited by EIA notification. In the POSCO EIA public
hearings are conducted under mostly unfavorable conditions for the public to
participate freely. First of all, the draft EIA report was not available for
the villagers before the POSCO public hearing. Heavy deployment of police of an
estimated 1000 police were stationed at the venue of the public hearing days
before the public hearing created a situation of panic among the people who
resist the project . Deployment of police force creates a situation of anxiety
and fear, rather than an atmosphere of peaceful public consultation especially
because of the conflict in interest of the state and local people in the issue.
Public consultation is prescribed for making the process more democratic while
such intervention of force and atmosphere of coercion cause tension for the
local people. Incidents like Kalinganagar and Nandigram[13] police
firings already left an impression of state using repressive mechanisms to
prevent public protest against industrial projects and its acquisition. The
presence of platoons of policemen prior to the public hearing and the conduct
of public hearing at Kujang which is almost 15 km away from the project site
reinforced the fear that local people had. This was a major cause for the
number of participants in the public hearing to be low. The purpose of
conducting a public hearing itself was defeated due to such lacuna in handling
public hearing by the authorities.
Forest
rights Act is comparatively new legislation that formed after considering many
historical facts and mistakes that happened during last decades towards the
forest dwelling communities. Ecology and biodiversity are recognized in a
broader framework which includes the forest dwelling communities too. The realization
that is provided by the FRA is fact that tribals and the other forest dwelling
communities are the integral part of the environment that meant to be protected
by the former environment protection Acts. A shift in the policy making that
reflected from the view of communitarian forest conservation ideas led to the
legalization of the rights that the forest dwellers had on the land and ecology
in which they were sustained on. Hence FRA is considered as a revolutionary Act
that gave the local communities a say on the resources on which they were
dependent on as well as co-existed with as the conservers. FRA seeks the
permission of Gram sabhas to start land Acquisition in Forest land areas.
According to Forest Conservation Act 1980, when projects fall within
forestlands, prior clearance is required from relevant authorities. State
governments cannot de-reserve any forestland or authorize its use for any
non-forest purposes without approval from the Central government. POSCO got its
final forest clearance from the MoEF on May 2nd 2011. Forest clearance needs to
be in accordance with the forest conservation Act 1980 and the Forest Rights
Act 2006. But POSCO got its dubious forest clearance from MoEF without clearing
the confusions that aroused about FRA implementation in the process. Forest
Rights Act with all the authority enforced in it for the empowerment and
participation of people in the decision making process became merit less due to
this act of MoEF. According to FRA provisions Gram Sabha is entitled to take a
decision about the land acquisition proposal. But in POSCO case State
government argued that the Palli Sabha(village council) meetings in which two
village councils denied permission to land acquisition were not valid. Former
Union Minister for Environment and Forests, Jairam Ramesh accepted the State
government's claim that the two Palli Sabha resolutions were invalid as they
were passed at meetings convened by the sarpanch without the authority of the
gram Panchayat, they were not recorded in a book kept for the purpose, and they
were signed by only 60-odd people in each of the villages. The forest clearance
that was given to POSCO needs to be studied thoroughly to understand how the
institutional provisions become ineffective under a situation of utter
inequality of power. State government had a very significant role to play in
the whole process. State government is supposed to implement the FRA and to
ensure that the rights of forest dwellers are protected in the whole process of
land acquisition for any non-forest purpose. In POSCO land acquisition case,
Orissa State government had an active role in facilitating the project which is
evidential from the MoU in which included the norm that, MoU, 6(xiii) “The
Government of Orissa will assist the Company in obtaining all clearances,
including forest and environment clearance and approval of the State Pollution
Control Board, and the Ministry of Environment and Forest, Government of India
under Forest (Conservation) Act, 1980 and Environmental (Protection) Act, 1986
for opening up the iron ore mines, laying roads, constructing township etc.”
State government's Act comes under questioning because POSCO Pratirodh Sangram
Samiti (PPSS) alleged that the State government is deliberately showing only the
signatures on the first page of the scanned document, while the hard copies of
the resolutions show that 1,638 people signed the resolution of Dhinkia and
1,265 people signed the resolution of Gobindpur. Rather than rejecting the two
Palli Sabha meetings that took place as invalid, state government didn't
implement FRA in the area which is obvious from the state government saying
that no Palli Sabha meeting was ever held otherwise. The resolutions sent by
the two Palli Sabhas have been rejected by the state government on the grounds
that the quorum was not met. However, the resolution sent by Orissa state
government was signed by only 34 people, which is not valid under law because
the gram sabha meeting for passing a resolution should be attended by at least
two-thirds of a village’s adult population. This discrepancy demonstrates how
there is a lack of standardized procedural neutrality in institutional
functioning and how there is an inbuilt bias in institutional functioning
towards private capital. Structure of the institution and the working of it are
equally important as the policy making. FRA recognizes the rights of the forest
dwellers and at least formally respects their right to take part in the
decision making process in development. But by treating POSCO case as “a
learning and evolving process” of FRA and by inconsistently rejecting
community’s decisions where they went against the POSCO and by accepting
decisions when favorable to POSCO, Mr.Jairam Ramesh has in effect redefined the
role of the regulatory institutions in relation to the rights of the forest
dwellers under the FRA passed by the parliament.
The
MoEF/MoTA Committee (Three member subcommittee of Environment Ministry's
"Committee to Study the Forest Rights Act" comprising of ArupjyotiSaikia,
Ravi Rebbapragada and Ashish Kothari) visited the proposed plant site and did
public consultation in Bhubaneshwar and had discussions with senior officials
of the Orissa government. Their report which was submitted in August 2010
clearly states that contrary to what the district administration was, there
were other Traditional Forest Dwellers (OTFDs) in the area. Committee report
concludes that “Any work related to the project in this area is a violation of
the FRA, and of the conditionality laid down by the MoEF in its forest
clearance 29 December 2009”[14]
Committee report recommended MoEF to “Ask the Orissa government to stop all
such work till the required processes under the FRA are completed, and till and
if Palli Sabha consent is obtained. And to withdraw the forest clearance
provided in December 2009.”53 By July 29, 2010 Environment Ministry constituted
a special four member Committee in order to investigate into the implementation
of Forest Rights Act in and around the plant site and also to look into the
status of implementation of the Rehabilitation and Resettlement package
pertaining to the project. This committee was chaired by former Environment
Secretary Meena Gupta. The Major part of the report of the committee went
against the claims of the state government and found that the forest clearance
was illegal and it recommended revoking the forest clearance given on December
2009. Sole member Meena Gupta submitted a dissenting report that contradicts
these findings and recommendations. Meena Gupta agrees with the majority report
recommending re- implementation of the Forest Rights Act in the region as the
procedure for FRA has not been done properly. However, in her view, the
environmental clearance need not be revoked; instead, additional conditions can
be applied before the construction starts. Following this report Forest
Advisory Committee recommended a temporary withdrawal of the forest clearance
on the grounds of violations of FRA on November 19, 2010. But by January 31,
2011MoEF gave permission to go ahead with the project with the final clearance
under the conditions. On February 21 Dhinkia Palli Sabha and on February 23
Gobindpur Palli Sabha convened and passed resolution rejecting consent for
diversion of forest land.
In
several POSCO project landmarked villages people claim that they had made both
individual and community claims which were approved in their Gram Sabha
resolutions which they had submitted to the concerned officials of the district
administration. According to the Majority Report of the MoEF committee that was
constituted to investigate into the proposal submitted by POSCO-India Pvt. Ltd.
“On March 23, 2008 the PalliSabhas in the three GPs of Dhinkia, Nuagaon and
Gadkujang formed forest rights committees with the exception of some villages,
viz., Bhuyanpal and Noliasahi, where the said committees were formed later”. As
per the FRA directives before processing applications for diversion of forest
land for any non-forest purpose, the proposal should be accompanied by “A letter
from each of the concerned Gram Sabhas, indicating that all
formalities/processes under the FRA have been carried out, and that they have
given their consent to the proposed diversion and the compensatory and
ameliorative measures if any, having understood the purposes and details of
proposed diversion” (exerted from MoEF circular issued on July 30, 2009 and
August 3rd, 2009). While this legislation exists as such, POSCO project got the
final forest clearance on Dec 29, 2009 without any such certificates being
provided by the State government or by the concerned Gram Sabha, regarding
either the completion of the Forests Rights Act process or the consent of the
PalliSabhas to the diversion of forest land. As per the committee report
“PalliSabhas of Dhinkia, Govindpur and Nuagaon met on Feb 5, Feb 6 and Feb 4th,
2010 respectively. They all passed similar resolutions rejecting diversion of
forest land for establishing the POSCO steel plant, asserting their eligibility
as other traditional forest dwellers (OTFDs) under the Forest Rights Act and
invoking their powers under section 5 of the Act to protect forests, wildlife,
biodiversity and their cultural and natural heritage”. Even after the
Pallisabhas proclaimed their right to protect their forest ecosystem, state
government sent their letter to MoEF stating that “no claims for settlement of
rights from tribals and traditional forest dwellers have been received. Since
no tribals or traditional forest dwellers are residing in the aforesaid area,
the question of settlement of rights of tribal people /other traditional forest
dwellers under the Forest Rights Act does not arise”. Hence what happened in
this case is the denial of rights of people by circumventing through
manipulations, the institutionalized guarantees to tribal populace.
Hence,
the gap that exists between the policies and realizations makes the principles
behind such policies as irrelevant and inactive. Most of the institutional
mechanisms failed to work in the prescribed way in POSCO case. This empirical
evidences need to be taken in to consideration while assessing the working of
principles and in reaching an assessment of the development model. Prominent
paradigm that prevails in the system influences the realized outcome to a great
extent. Even though much legislation are there to protect the interests of
people and environment, as in the POSCO case those legislations and
institutional measures may not work properly and the outcome can be contrary to
the principles that prevail . As Sen suggests in his Idea of Justice (2009)
actual realizations and accomplishments needs to be focused in assessing the
real impact of such arrangements that exists.
In
the POSCO case, people's representation and democratic ways of opposition is
ignored by the state and the central governments in favor of the development
regime that supports private investment at any cost. Both environmental and
social costs of the project are estimated as much higher when compared to the
benefits, the project can bring to the economy. Even after the local
self-governments (pallisabhas) expressed their dissent in diverting land for
the project, central and state governments plan to go ahead with the project.
This is a gross violation of the democratic rights and powers, thrust upon local
governments as per the three-tier system of governance in India.
To
reduce the gap existing in the integration of policy and practice
Policy
making is more close to the academic understanding of development and the new
conflicts arising out of current model of development, especially in terms of
environmental and social sustainability. But policy enactment does not ensure
the realization of its essence. As a result even the valuable understandings of
research in development studies go in vain. Industrialization and high GDP
generation is the widely accepted norm of development, without acknowledging
the other factors like real human development through capability expansion,
sustainability of the process of development and ultimately the well-being of
people. Mainly politicians and government officials try to attain maximum
investment and income generation in the economy which can be easily transformed
to infrastructure and power sector expansion. This dominant stigma works
against the true spirit of expansion of opportunities people actually have.
Communities that get affected by these kinds of one sided policy decisions
oppose such “developmental projects” and that result in strong protests from
people which normally gets aggravated by the forceful land acquisition efforts
from the part of state. Redefinition of property rights and community rights over
forest resources and its significance in the preservation of natural resources
was the result of integration of research into policy. But practice of the same
needs rigid institutional set ups. Current institutions and institutional
mechanisms are not efficient to implement the policy directives, when the
dominant norm of development and industrial expansion comes in conflict with
the real human development and rights protection (both civil rights and
property rights). This can be resolved to a great extent if the power to take
decisions about a new development project is shared with people more equally,
especially with those who will get directly affected by the project. Under such
a condition, policy implementation will be closely watched by local self
governments with the decision making power they are assigned with.
[1]
Pandit
Jawaharlal Nehru himself proclaimed that “Bhakra is the new temple of resurgent
India. It is the symbol of India’s progress.”In the case of Bhakra dam 7,206
families were affected comprising about 36,000 persons in 371 villages that
were displaced and not properly resettled but then the spirit of nation
building helped the government in pacifying those who has undergone
displacement. Nehru said to the displaced persons of Hirakund Dam in 1948 that
“If you are to suffer, you should suffer in the interest of the nation”
[2]
“Other traditional forest dweller” means
any member or community who has at least for 3 generations prior to
the 13th day of December, 2005 primarily resided
in and who depended on the forest, or forest land for bona fide
livelihood
needs.
[3]
Means a village assembly which shall
consist of all adult members of a village and in case of states having no
Panchayats, Padas, Todas and other traditional village institutions
and elected village committees, with full and
unrestricted participation of women (FRA, 2006 chapter 1, Def: 2g)
[4]
National Council for Applied Economic
Research (NCAER) in 2007 done a cost‐benefit analysis of the POSCO project and
submitted their report saying that “apart from
representing the least cost technology, POSCO’s project would yield attractive
returns. The economic impact of the project is estimated at USD 2.5 billion at
the test discount rate of 12 per cent”. Odisha state government uses this
report to justify the POSCO project and showcase that the project is essential
for the state economy to develop.
[6]
P.p. 127. Report of the Committee
Constituted to Investigate into the proposal submitted by POSCO India Pvt.
Limited
for establishment of an Integrated Steel Plant and Captive Port in
Jagatsinghpur District, Orissa
[7] The Mining
Zone People’s Solidarity Group is an international research group focused on
India, with core interests in new economic policy. They have done a comprehensive
analysis of the POSCO project as well as a critical evaluation of NCAER
cost-benefit report. Their report “Iron and Steel: The POSCO-India story”
published in 2010 uses unconventional frameworks in the analysis.
[9]
It is evidential in many cases like
Vedanta project(REPORT OF THE FOUR MEMBER COMMITTEE FOR
INVESTIGATION INTO THE PROPOSAL SUBMITTED BY THE ORISSA MINING COMPANY
FOR BAUXITE MINING IN
NIYAMGIRI. August 16, 2010 chaired by Dr N C Saxena), Jindal steel’s
coal mining project in Chhattisgarh (Green
tribunal
sets aside clearance granted to Jindal, The Hindu, 21 April, 2012) etc
[11]
Chaturvedi.R. (Oct.2004).Environmental
Hearings: Participatory Forums or a Mere Procedure? Economic and
Political
Weekly(39)42,
4616-4619.
[12]
Report of the Committee Constituted to
Investigate into the proposal submitted by POSCO India Pvt. Limited for
establishment
of an Integrated Steel Plant and Captive Port in Jagatsinghpur District, Orissa
Pp. 43
[13]
Conflict between protesters and police
men regarding the land acquisition process caused total of 28 deaths in
these places( 14 persons in Kalingnagar (January 2, 2006) and 14
persons in Nandigram died in Police firing on
March 14,2007). Police open fire at proteters, The Hindu,May 13,2010.
http://en.wikipedia.org/wiki/Nandigram_violence
[14]
Report of visit to Jagatsinghpur (site of
proposed POSCO project), Orissa, 23-24 July 2010. MoEF/MoTA
Committee
on Forest Rights Act Report